An Early-Intervention Framework for Controlling Cost, Schedule and Rework in Building Projects

  • Unique Paper ID: 209353
  • Volume: 13
  • Issue: 5
  • PageNo: 1660-1668
  • Abstract:
  • Design changes are a persistent feature of building projects and can generate cascading effects across cost, schedule, procurement, coordination, quality and rework. Existing research has extensively examined the causes and consequences of design changes, while recent studies have increasingly explored quantitative and digital approaches for assessing their impacts. However, a practical need remains for a structured decision process that can be applied when a change is first proposed, before its effects propagate into construction activities. This study develops a Design Change Early-Intervention Framework for the design–construction interface. A structured literature synthesis was undertaken using peer-reviewed research on design change, rework, change management, BIM-enabled change assessment, schedule impact and proactive risk management. The literature was thematically organized around five decision requirements: change identification, affected-scope mapping, impact assessment, decision authorization, and controlled implementation. The resulting framework introduces seven change-management gates through which each proposed design change is screened for its cause, affected disciplines, cost exposure, schedule exposure, procurement consequences, quality implications and rework potential. The framework emphasizes multidisciplinary review before site implementation and establishes a feedback mechanism through which completed changes contribute to project learning. The study contributes a practical conceptual model linking architectural decision-making with construction project control. Future empirical research should validate the framework using project records and measurable indicators such as change-cycle time, rework hours, cost variance, schedule variance and RFI frequency.

Copyright & License

Copyright © 2026 Authors retain the copyright of this article. This article is an open access article distributed under the Creative Commons Attribution License which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

BibTeX

@article{209353,
        author = {MOHAMMED SHARUQ UDDIN},
        title = {An Early-Intervention Framework for Controlling Cost, Schedule and Rework in Building Projects},
        journal = {International Journal of Innovative Research in Technology},
        year = {2026},
        volume = {13},
        number = {5},
        pages = {1660-1668},
        issn = {2349-6002},
        url = {https://ijirt.org/article?manuscript=209353},
        abstract = {Design changes are a persistent feature of building projects and can generate cascading effects across cost, schedule, procurement, coordination, quality and rework. Existing research has extensively examined the causes and consequences of design changes, while recent studies have increasingly explored quantitative and digital approaches for assessing their impacts. 
However, a practical need remains for a structured decision process that can be applied when a change is first proposed, before its effects propagate into construction activities.
This study develops a Design Change Early-Intervention Framework for the design–construction interface. A structured literature synthesis was undertaken using peer-reviewed research on design change, rework, change management, BIM-enabled change assessment, schedule impact and proactive risk management. The literature was thematically organized around five decision requirements: change identification, affected-scope mapping, impact assessment, decision authorization, and controlled implementation. 
The resulting framework introduces seven change-management gates through which each proposed design change is screened for its cause, affected disciplines, cost exposure, schedule exposure, procurement consequences, quality implications and rework potential. The framework emphasizes multidisciplinary review before site implementation and establishes a feedback mechanism through which completed changes contribute to project learning. The study contributes a practical conceptual model linking architectural decision-making with construction project control. Future empirical research should validate the framework using project records and measurable indicators such as change-cycle time, rework hours, cost variance, schedule variance and RFI frequency.},
        keywords = {Design change; Construction management; Change risk; Rework; Design–construction interface; Project control.},