A Sustainable Approach to Construction Delay Analysis Using Window Method and Primavera P6

  • Unique Paper ID: 181698
  • Volume: 12
  • Issue: 1
  • PageNo: 5253-5260
  • Abstract:
  • Delays in construction projects significantly impact costs, schedules, and stakeholder confidence. This study critically examines the causes, impacts, and analysis methods of delays, using literature review, stakeholder surveys, and forensic tools. The Window Analysis Method with Primavera P6 was applied to assess critical path shifts and delay responsibilities in a luxury golf and leisure project. Key delay factors included late drawings, permit issues, and BIM discrepancies. Findings reveal that over 70% of delays were avoidable through better coordination and planning. The study promotes best practices like early risk detection and digital project tracking, aligning with SDG 9 and SDG 11 by supporting resilient infrastructure and sustainable urban development.

Copyright & License

Copyright © 2025 Authors retain the copyright of this article. This article is an open access article distributed under the Creative Commons Attribution License which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

BibTeX

@article{181698,
        author = {Qudsia Fatima and Dr. Gugulothu Vikas and MOHAMMED JALAL UDDIN},
        title = {A Sustainable Approach to Construction Delay Analysis Using Window Method and Primavera P6},
        journal = {International Journal of Innovative Research in Technology},
        year = {2025},
        volume = {12},
        number = {1},
        pages = {5253-5260},
        issn = {2349-6002},
        url = {https://ijirt.org/article?manuscript=181698},
        abstract = {Delays in construction projects significantly impact costs, schedules, and stakeholder confidence. This study critically examines the causes, impacts, and analysis methods of delays, using literature review, stakeholder surveys, and forensic tools. The Window Analysis Method with Primavera P6 was applied to assess critical path shifts and delay responsibilities in a luxury golf and leisure project. Key delay factors included late drawings, permit issues, and BIM discrepancies. Findings reveal that over 70% of delays were avoidable through better coordination and planning. The study promotes best practices like early risk detection and digital project tracking, aligning with SDG 9 and SDG 11 by supporting resilient infrastructure and sustainable urban development.},
        keywords = {Window Analysis, Primavera P6, forensic delay analysis, time impact analysis, extension of time (EOT), critical path method, SDG 9& 11, sustainable infrastructure, delay mitigation strategies.},
        month = {June},
        }

Cite This Article

  • ISSN: 2349-6002
  • Volume: 12
  • Issue: 1
  • PageNo: 5253-5260

A Sustainable Approach to Construction Delay Analysis Using Window Method and Primavera P6

Related Articles